Traffic Engineering Implemented on Jalan Gajah Mada and Jalan Hayam Wuruk
Reported by Aldi Geri Lumban Tobing | Translated by Maria Inggita
Jakarta Transportation Agency (Dishub) implemented traffic engineer on Jalan Gajah Mada and Jalan Hayam Wuruk due to relocation work of clean water pipeline utility network on those two roads from February 23 until April 30, 2021.
Road users were advised to avoid these roads and follow traffic signs and instructions from officers on the field
Jakarta Dishub Head, Syafrin Liputo mentioned, on February 23-March 30, 2021 the relocation work will carry out on Jalan Gajah Mada, right on Transjakarta route, that will cause Transjakarta bus to apply mix traffic along the work area. As well as on Jalan Zainul Arifin and lane 1 and 2 of Jalan Gajah Mada that will be narrowed due to relocation work.
Anies Hopes 2021 Lintas Jaya Operation to Create Culture of Orderly Traffic"This work is carried out on Jalan Hayam Wuruk, on Transjakarta route, thus Transjakarta bus will mix traffic along the work area," he explained, Wednesday (2/24).
From February 23 to March 30, 2021, this work will be carried out on Jalan Pancoran by reducing vehicle lanes.
Then, on February 28-March 15, when the work is carried out on lane 1 of Jalan Gajah Mada, it will cause reduction in vehicle lanes along the work area.
"On March 1-30, relocation work on Jalan Gajah Mada and Transjakarta lane on Jalan Hayam Wuruk, Transjarta bus traffic mix along the work area," he added.
From March 30 until April 1, work on Jalan Gajah Mada and Transjarta bus traffic mix along the work area.
"On April 1-30, relocation work will be carried out on Jalan Hayam Wuruk lane 2, thus it will cause road narrowing," he conveyed.
Road users were advised to avoid these roads and follow traffic signs and instructions from officers on the field.
"Traffic will return to normal after relocation work finished," he closed.